About The Author:
Robert A. Olson is a partner in the law firm of
Brown, Olson & Gould, P.C. which maintains a nationwide practice in energy law,
public utility law and related commercial transactions.
He can be reached at:
Brown, Olson & Gould, PC
2 Delta Drive
Suite 301
Concord, NH 03301
rolson@bowlaw.com
(603) 225-9716
|
|
September 2005
Idaho to Scrutinize PURPA Rates For Wind QFs
by Robert Olson and Maria Reinemann -- Brown, Olson and Wilson, P.C.
(originally published by PMA OnLine Magazine:
2005/10/14)
The federal Public Utility Regulatory Policies Act
(“PURPA”) requires regulated utilities to buy renewable power generated by
qualifying small power production facilities (“QFs”) at an “avoided cost
rate,” i.e., a rate that reflects the cost the utility avoids by not having
to generate the electricity itself or buy the electricity from some other
source. It also requires state authorities to publish standard avoided cost
rates that apply to small QFs. In a recent order, the Idaho Public Utilities
Commission (the “PUC”) decided that its published avoided cost rate should
be adjusted to take into account the intermittent nature of wind generation
when applied to QFs selling wind-generated power (“Wind QFs”). In the Matter
of the Petition of Idaho Power Company for an Order Temporarily Suspending
Idaho Power’s PURPA Obligation to Enter Into Contracts to Purchase Energy
Generated by Wind-Powered Small Power Production Facilities, Case No. IPC-E-
05-22, Interlocutory Order No. 29839 (Idaho PUC, August 4, 2005) (the
“Order”). According to the Order, this represents a departure from the PUC’s
past practice, which has been to resist developing separate avoided cost
rates targeted to individual QF generating technologies.
The petitioning utility argued that the published avoided cost rate of $61
per megawatt hour overstates the cost a utility avoids when it buys
electricity from Wind QFs because it ignores the utility’s cost for back-up
power required to integrate intermittent wind generation into the utility’s
system. One analysis showed that for every 1,000 megawatts of intermittent
wind generation, a utility must have an additional 640 megawatts of firm
electricity generation on hand to maintain adequate system reliability.
The utility further pointed to a dramatic increase in QF wind generation as
exacerbating the problem. According to the utility, there was only 1
megawatt of QF wind generation under contract in December of 2004, and there
are now 61.5 megawatts of generation under contract, with applications for
another 21.5 megawatts pending before the commission and developers
currently planning projects to produce another 193 megawatts of wind
generation.
Finally, the utility argued that the excessive avoided cost rate inflated
the competitive bids of developers of large wind-generation projects. As one
witness explained, “wind projects are unique because they consist of
multiple wind turbines, each usually with a capacity of about 1.5 megawatts,
spread over many acres,” that can be clustered to form relatively large or
small projects. With Idaho’s eligibility threshold for the published avoided
cost rate set at 10 megawatts, “there is little incentive for the developer
of a wind project to bid a price” less than the published avoided cost rate
if the project can be reconfigured to fall below the threshold and qualify
for the published avoided cost rate.
Although the PUC was not persuaded that the competitive bids from wind
developers were, in fact, influenced by the published avoided cost rate, the
PUC agreed that the published rate should be adjusted for Wind QFs to
reflect a utility’s cost to integrate intermittent wind generation.
The Order deferred determination of the amount of adjustment to further
proceedings. The utility asked the PUC to suspend the PURPA obligation to
purchase Wind QF generation pending a determination of the adjusted rate.
The utility argued that developers would reconfigure their projects to fall
below the eligibility threshold for the published avoided cost rates in an
attempt to qualify for the current rates before they are changed, resulting
in an “unmanageable influx of generation.” The PUC denied the request, but
instead sharply reduced the eligibility threshold from 10 megawatts to
PURPA’s required threshold of 100 kilowatts.
Robert A. Olson is a partner in the law firm of Brown, Olson &
Gould P.C.
which maintains a nationwide practice in energy law, public utility law and related
commercial transactions. He can be reached at:
Brown, Olson & Gould, PC
2 Delta Drive, Suite 301
Concord, NH 03301
rolson@bowlaw.com | (603) 225-9716
|